Elevator renovation - week 2
During week 2, Akdemiska hus will change the rails on elevator doors. If you require elevator access during this period, you may need to use elevators in adjacent buildings.
Timetable for elevator renovation
Location: Buildings 11, 21, 31, 51 and 99
Time: Week 2 (one day per elevator)
The replacement takes place in the following order:
House | Date: Day of the week | Day of the week | |
---|---|---|---|
51 | 7/1 | Tuesday | |
31 | 8/1 | Wednesday | |
21 | 9/1 | Thursday | |
11 | 10/1 | Friday | |
99 | Scheduled later in the week |
Please note that these times are preliminary. Each replacement is expected to take one day per elevator, but in some cases, the work may take longer. This means that exact days for shutdowns cannot be guaranteed. The work is being carried out by the contractor Kone.
The work will be carried out by the contractor Kone.
Alternative elevators
Floors 1-3 in buildings 11 and 31 and floors 1-2 in buildings 99 and 21 can be reached via an elevator in a nearby building.
Contact
If you have any questions, please contact: fastighet@hig.se.